NMU Current Projects

Infrastructure Investment from 2025-2027 $18,863,690

  • Project Status
    • Construction in progress
    • 45% complete
  • Works to Date
    • Moving-Bed Biofilm Reactor (MBBR) structural works, deliveries of process and mechanical equipment’s.
    • Electrical, controls, MCC/VFD, and harmonic study reviews
  • Estimated completion
    • June 30, 2027.
  • Outcome
    • Near-term wastewater treatment capacity and help inform the roadmap for the next phase of expansion planning, enabling further development within Drayton and Moorefield.

MBBR tank walls

MBBR tank construction in -progress

MBBR tank suspended slab (Ground floor) Rebar


MBBR tank suspended slab concrete placed

 

Infrastructure Investment from 2025-2027 $16,144,132

  • Project Status
    • Construction in progress
    • 43% complete
  • Works to date include
    • Overflow tank, wet wells, structural concrete preparations, site works, forcemain-related coordination, and ongoing review of mechanical, electrical, and controls submittals.
    • Electrical study updates, including short-circuit and harmonic reviews, are being completed to support MCC/VFD approvals and equipment release.
  • Estimated completion
    • July 2027
  • Outcome
    • Project will improve wastewater pumping reliability and provide upgraded infrastructure to support current and future servicing needs.

Drayton Wastewater Pumping Station (early stage)


Site Grading - Early Construction Stage


Control building strip footings and shoring sheet piles for overflow tank and SPS wet well


Control building walls

Infrastructure Investment $5,738,245

  • Project Status
    • Construction in progress
    • 32% complete
  • Works to date include
    • Site servicing, standpipe installation, coordination of wellhouse/building works, watermain and process piping-related activities.
    • Hydro One coordination has transitioned into the construction phase, with Graham carrying construction-side coordination
  • Estimated completion
    • April 2027
  • Outcome
    • Project supports long-term water system reliability for the village of Moorefield, through renewal of water supply, treatment, pumping, electrical, controls, and related site infrastructure

Construction (early stage)


Pump house extension mud slab


Pump house extension rebar


Pump house extension slab


Underground works - Watermain Installation


Underground power and communication ducts


Standpipe #2 tank annular footing


Standpipe #2 (Glass -fused-to-steel bolted tank) foundation slab


Standpipe #2 (Glass-fused-to-steel bolted tank) construction in-progress


Standpipe #2 (GFS tank) construction in-progress (not yet final tank height)

22079 Infrastructure Investment $236,025 

22082 Infrastructure Investment $374,484

  • Project Status
    • Project is currently in the conceptual design phase.
    • Paused pending further direction on preferred servicing approach, development timing, and municipal priorities.
  • Estimated completion
    • Fall 2027
  • Outcome
    • Project intended to support future development and servicing needs in the northwest Drayton area near Drayton Industrial Drive.

22078 Infrastructure Investment $1,525,568.50

22081 Infrastructure Investment $426,921.50 

  • Project Status
    • Project has advance through preliminary design phase and is advancing towards a more detailed design
    • Project is currently paused pending advancement of the related development application and confirmation of final servicing needs.
  • Estimated completion
    • Fall 2027
  • Outcome
    • Project intended to support future growth by extending municipal water and sanitary sewer servicing.

Infrastructure Investment $466,549